Restaurant-Ready Assessment · Batch of 5

Pipeline readiness

2 of 5 sites carry pro-forma risk.

3 are viable. Ranked by readiness below.

5 of 5 shown

Select up to 2 sites to compare.

  1. 01

    Schertz, TX

    Ready
    Buildout
    $310,000–$385,000
    Open by
    Q2 2027 · 9 mo
  2. 02

    Selma, TX

    Ready with upgrades
    Buildout
    $421,000–$512,000
    Open by
    Q3 2027 · 11 mo
    • Grease
    • Service
    • Hood path
    • Gas
  3. 03

    Cibolo, TX

    Ready with upgrades
    Buildout
    $352,000–$430,000
    Open by
    Q3 2027 · 10 mo
    • Service
  4. 04

    Live Oak, TX

    Not viable as-is
    Buildout
    $689,000–$845,000
    Open by
    Q1 2028 · 16 mo
    • Grease
    • Gas
    • Hood path
    • Structural

    Pro-forma risk. No hood path and no viable route for one — the demising wall carries load and the roof structure won't take a new curb without reinforcement. $240K over the pro forma before the first fixture.

  5. 05

    Universal City, TX

    Not viable as-is
    Buildout
    $724,000–$910,000
    Open by
    Q1 2028 · 17 mo
    • Grease
    • Service
    • Gas
    • Hood path

    Pro-forma risk. Never a restaurant. White box with 200A service, no grease infrastructure, no gas beyond a 1" line. Every system starts at zero.