Status

Maitre sends one update per milestone. There is nothing to log into — the email is the record. This is the last one sent on 4120 Corridor Crossing, Suite 100.

Email update

Restaurant-Ready Assessment — 4120 Corridor Crossing, Suite 100

From
Maitre Assessments <assessments@maitre.co>
Subject
Your report is ready — Selma, TX 78154
Sent
July 9, 2026

Your Restaurant-Ready Assessment for 4120 Corridor Crossing, Suite 100 in Selma, TX is complete. Below is the whole record: what we received, when the engineer walked the space, and what came back. Nothing in the report was inferred from the listing or from photographs.

  1. Complete. Received

    June 26, 2026

    Property details and plans logged. Assigned to Halvorsen Mechanical.

  2. Complete. Site visit scheduled

    July 2, 2026

    Engineer walked the space with the property manager. Panel, gas meter, hood, and sanitary rough-in documented.

  3. Complete. Engineering review

    July 7, 2026

    Fixture schedule run against code. Cost ranges built from three subcontractor bids per system.

  4. Complete — this is the latest step. Report ready

    July 9, 2026

    Your Restaurant-Ready Assessment is complete.

    Read the assessment

Report ready

July 9, 2026